Shown below are all the current construction progress photographs of the projects, in reverse chronological order. Enlarged images can be seen by clicking any of these thumbnails.

3.6.19_H04-2
March 06, 2019
Deck construction continues on the west side of the new Aramingo Avenue bridge over Frankford Creek at the Betsy Ross Bridge Interchange.
3.6.19_GIR-2
March 06, 2019
Support piers for the west half of the Aramingo Avenue bridge over Girard Avenue will be demolished so that half of the new bridge can be constructed.
3.6.19_AF1-2
March 06, 2019
Workers install an electrical duct bank on Richmond Street north of Allegheny Avenue that will be used to power the SEPTA Route 15 Trolley following reconstruction of Richmond Street in Port Richmond.
3.5.19_GIR-3
March 06, 2019
Pier stems to support a section of the new southbound viaduct at Girard Avenue.
3.5.19_AF1-1
March 06, 2019
Melvale Street is widened for additional Richmond Street parking. It will be paved this spring.
2.19_BS4-3
February 04, 2019
Workers weld sections of a new gas main being installed under Aramingo Avenue at the Betsy Ross Bridge Interchange.
2.19_AF1-3
February 04, 2019
A crew installs an electrical duct bank under Richmond Street that will be used to power the Route 15 Trolley.
2.19 GR4-4
February 04, 2019
Excavation at the Aramingo Avenue bridge over Girard Avenue
2.19_GR4-3
February 04, 2019
The retaining wall that helps support the Aramingo Avenue Bridge over Girard Avenue is being replaced as part of the GR4 project.
2.19_GR4-1
February 04, 2019
Excavation for a pier foundation for the new southbound viaduct at Girard Avenue.