Current Progress Photos

Shown below are all the current construction progress photographs of the projects, in reverse chronological order. Enlarged images can be seen by clicking any of these thumbnails.

7.19.17_BR0-1
July 21, 2017
Barrels mark the construction zone along Torresdale Avenue near Adams Avenue where PennDOT is installing new water lines as part of the Adams Avenue Connector.
7.19.17_CPR-7
July 21, 2017
A crew finishes a section of sidewalk at the Princeton Avenue extension under I-95.
7.19.17_GIR-Water
July 21, 2017
A water truck sprays the Girard Interchange construction areas to keep the dust down.
6.21.17_BR0-1
June 23, 2017
Workers position barrier along the new approach to the southbound off-ramp to the Betsy Ross Bridge.
6.21.17_GIR-2
June 23, 2017
The old retaining wall along I-95 north at Colombia Avenue near the Girard Avenue Interchange is being replaced by the approach to the new northbound off-ramp to Richmond Street.
6.26.17_GIR-1
June 23, 2017
With the old northbound off-ramp removed, excavators are clearing the area to start construction on the southern end of the new northbound viaduct.
6.12.17_GIR-1
June 13, 2017
Demolition of a retaining wall at Columbia Avenue and Richmond Street for construction of the approach to the new northbound off-ramp at Girard Avenue.
6.12.17_H04-1
June 13, 2017
Water main installation along Torresdale Avenue near Adams Avenue: The work is part of the project to improve and extend Adams Avenue between Torresdale and Aramingo avenues.
6.12.17_BR0-3
June 13, 2017
The widened on-ramp from Aramingo Avenue to I-95 north and south.
6.5.17_GIR-1
June 05, 2017
The old northbound I-95 ramp to Delaware Avenue at the Girard Avenue Interchange is demolished. Northbound traffic is exiting at a new ramp to Richmond Street nearby.