• Follow Us on Twitter

Current Progress Photos

Shown below are all the current construction progress photographs of the projects, in reverse chronological order. Enlarged images can be seen by clicking any of these thumbnails.

8.15.18_GR4-1
August 15, 2018
Micro-piles drilled, not hammered, into place for a pier foundation for the new southbound viaduct between Ann and Palmer streets.
8.15.18_H04-1
August 15, 2018
The new intersection of the Adams Avenue Connector and the ramps to I-95 at the Betsy Ross Bridge Interchange.
8.15.18_BS4-1
August 15, 2018
A coffer dam - which allows for foundation construction in a stream -- in place for construction of an abutment for the new Aramingo Avenue bridge over the Frankford Creek at the Betsy Ross Bridge Interchange.
7.18.18_H04-1
July 20, 2018
An inspector looks on as rock is excavated for construction of the west side of the new Aramingo Avenue bridge over Frankford Creek at the Betsy Ross Bridge Interchange.
7.18.18_GIR-4
July 20, 2018
During early stage construction on the contract to replace the southbound viaduct at Girard Avenue, a crew installs micro-piles in the construction of support piers for the new structure. PennDOT is using micro-piles for construction adjoining residential neighborhoods to reduce noise during construction.
7.18.18_GIR-3
July 20, 2018
A section of the northbound viaduct at Girard Avenue is prepared for concrete deck placement.
6.7.18_GIR-2
June 12, 2018
A drilling rig is set up to begin installing "micro piles" that will support the foundations of new columns that will support the new southbound viaduct at the Girard Avenue Interchange.
6.7.18_GIR-4
June 12, 2018
New LED lighting is installed on the under-side of the new northbound viaduct near Lehigh Avenue at the Girard Avenue Interchange.
6.7.18_AF1-3
June 12, 2018
A crew guides a new PECO pole into place along Richmond Street in Port Richmond. The poles are being replaced under the first stage of PennDOT's $32 million project to improve Richmond Street to enhance surface street travel at the Allegheny Avenue Interchange.
5.9.18_BS4-4
May 10, 2018
Pile driving at the Aramingo Avenue bridge over Frankford Creek at the Betsy Ross Interchange