Current Progress Photos

Shown below are all the current construction progress photographs of the projects, in reverse chronological order. Enlarged images can be seen by clicking any of these thumbnails.

12.18_BS4-4
December 03, 2018
Workers backfilling an abutment wall at the Aramingo Avenue bridge over Frankford Creek at the Betsy Ross Bridge Interchange.
12.18_GR4-2
December 03, 2018
Inserting micro-piles for the southbound viaduct at Girard Avenue.
12.18_AF1-3
December 03, 2018
Backfilling a utility trench on Richmond Street.
10.29.18_GR4-2
November 05, 2018
Workers have begun dismantling the southbound viaduct at the Girard Avenue Interchange.
10.29.18_BS4-1
November 05, 2018
Construction of an abutment for the western half of the Aramingo Avenue bridge over Frankford Creek at the Betsy Ross Bridge Interchange.
10.29.18_AF1-2
November 05, 2018
Work is underway to proved parking on Melvale Street as part of the improvements to Richmond Street in Port Richmond, the first stage of the reconstruction of I-95 at Allegheny Avenue.
9.27.18_GIR-2
October 01, 2018
Worker pour a column stem that will support a section of the new southbound viaduct at Girard Avenue.
9.27.18_BS4-1
October 01, 2018
A crew installs a drainage inlet for the widened Aramingo Avenue at the Betsy Ross Bridge Interchange.
9.27.18_AF1-3
October 01, 2018
New water main awaits installation along Richmond Street.
9.6.18_BS4-2
September 10, 2018
A crew installs storm water pipes as part of the widening of Aramingo Avenue near the Betsy Ross Bridge Interchange ramps.