Project Specifics
In addition to improving the ramp access and surface road circulation at the Betsy Ross Bridge/Aramingo Avenue Interchange, I-95/ BRI will improve traffic flow for the estimated 180,000 motorists who drive each day on I-95.
I-95 mainline improvements
- Reconstruction of four through lanes in each direction and widening of the median and shoulders.
- Reconstruction or repair of 28 northbound and southbound bridges.
- Construction of northbound and southbound collector-distributor lanes to serve traffic entering and exiting at Aramingo Avenue and the Betsy Ross Bridge.
At Betsy Ross Bridge/Aramingo Avenue Interchange
- Build a new road that connects Aramingo Avenue to Adams Avenue.
- Build new ramps to and from Aramingo Avenue and I-95 and the Betsy Ross Bridge.
- Build a new off-ramp from I-95 North to Orthodox Street that provides access to Aramingo Avenue.
- Close the existing on-ramp from Aramingo Avenue to I-95 South.
- Close the existing off-ramp from I-95 North to Aramingo Avenue.